Projects — TIB Project Information
TIB Project Information
Town of Yacolt's FY 2014 Overlay Project
2-W-951(003)-1
2-W-951(003)-1
FY 2014 Overlay Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $10,986
County: Clark | Legislative District: 18 | Project Length: 0.06 | TIB Engineer: Chris Langhoff | Last Payment Date: 03/03/2014
Project Information
Lead Agency | YACOLT |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 18 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.06 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Pete Roberts |
Contact Email | pete.roberts@centurytel.net |
TIB Engineer | Chris Langhoff |
Last Payment Date | 03/03/2014 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 05/01/2013 | 06/13/2013 |
Bid Auth. Approval | 03/01/2014 | 06/13/2013 |
Construction Approval | 08/01/2013 | 08/01/2013 |
Project Closeout | 02/15/2014 | 02/19/2014 |
Audit Date | 03/03/2014 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 2,628 | 0 |
Right of Way | 0 | 0 |
Total Design | 2,628 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 13,797 | 8,075 |
Other Construction | 0 | 2,911 |
Total Construction | 13,797 | 10,986 |
Funding Surplus | - 5,439 | |
Total TIB Funding | 10,986 | 10,986 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YACOLT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will repair minor areas of failed pavement and place a 2 inch overlay on Amro Avenue from Wilson to Humphrey.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |