City of La Center's FY 2009 Overlay Project
2-W-949(001)-1
2-W-949(001)-1
FY 2009 Overlay Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $114,848
County: Clark | Legislative District: 18 | Project Length: 1.15 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/01/2009
Project Information
Lead Agency | LA CENTER |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 18 |
Congressional District | 3 |
Federal Route Number | J069 |
Project Length | 1.15 mi. |
ADT | 1,500 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Bart Stepp |
Contact Email | bstepp@ci.lacenter.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 01/01/2009 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/01/2008 | 04/07/2008 |
Bid Auth. Approval | 01/01/2008 | 04/07/2008 |
Construction Approval | 09/01/2008 | 08/15/2008 |
Project Closeout | 10/31/2008 | 12/22/2008 |
Audit Date | 01/01/2009 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 2,165 |
Right of Way | 0 | 0 |
Total Design | 0 | 2,165 |
Construction Engineering | 0 | 4,031 |
Construction Contract | 120,222 | 375,865 |
Other Construction | 0 | 0 |
Total Construction | 120,222 | 379,896 |
Funding Surplus | - 5,374 | |
Total TIB Funding | 114,848 | 382,061 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LA CENTER | 267,213 | 69.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 267,213 | 69.9% |
Project Description
The project consists of grinding, preleveling and 2 in overlay of East 4th Street between NW Pacific Highway and the east city limits.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |