TIB Project Information

Town of Wilkeson's Citywide Crack Seal

2-P-816(003)-1

2-P-816(003)-1
Citywide Crack Seal

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $8,500

County: Pierce   |   Legislative District: 31   |   Project Length: 0.60   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 03/15/2023

Project Information

Lead Agency WILKESON
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 31
Congressional District 8
Federal Route Number 9999
Project Length 0.60 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Marie Wellock
Contact Email Clerk@townofwilkeson.com
TIB Engineer Greg Armstrong
Last Payment Date 03/15/2023

Project Schedule

  Target Date Actual Date
Project Selection Date   06/30/2022
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 07/15/2022 07/14/2022
Bid Auth. Approval 07/15/2022 07/14/2022
Construction Approval 07/15/2022 07/14/2022
Project Closeout 06/30/2023 03/09/2023
Audit Date   03/15/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 3,750 8,500
Other Construction 0 0
Total Construction 3,750 8,500
     
Funding Increase 4,750  
Total TIB Funding 8,500 8,500

Local Funding Partners

Funding Amount Percent
WILKESON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

3000 Linear feet of Crack Seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments