Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Buckley's 2017 Emergency Pavement Repair Project

2-P-808(004)-1

2-P-808(004)-1
2017 Emergency Pavement Repair Project

Various Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $47,935

County: Pierce   |   Legislative District: 31   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/13/2017

Project Information

Lead Agency BUCKLEY
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 31
Congressional District 8
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dave Schmidt
Contact Email dschmidt@cityofbuckley.com
TIB Engineer Greg Armstrong
Last Payment Date 11/13/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   05/12/2017
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 06/15/2017 05/31/2017
Bid Auth. Approval 06/15/2017 05/31/2017
Construction Approval 06/15/2017 05/31/2017
Project Closeout 08/31/2017 10/31/2017
Audit Date   11/13/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 45,486 50,458
Other Construction 0 0
Total Construction 45,486 50,458
     
Funding Increase 2,449  
Total TIB Funding 47,935 50,458

Local Funding Partners

Funding Amount Percent
BUCKLEY 2,523 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 2,523 5.0%

Project Description

See approved repair list.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments