TIB Project Information
City of Moxee's FY 2019 Overlay Project
2-E-943(004)-1
2-E-943(004)-1
FY 2019 Overlay Project
Multiple Locations
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $257,822
County: Yakima | Legislative District: 15 | Project Length: 0.45 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/01/2018
Project Information
Lead Agency | MOXEE |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.45 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Byron Adams |
Contact Email | byron.adams@co.yakima.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/01/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 01/08/2018 |
Bid Auth. Approval | 03/29/2018 | 03/28/2018 |
Construction Approval | 04/26/2018 | 04/30/2018 |
Project Closeout | 12/31/2018 | 09/17/2018 |
Audit Date | 10/01/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 30,000 | 31,906 |
Right of Way | 0 | 0 |
Total Design | 30,000 | 31,906 |
Construction Engineering | 30,000 | 28,919 |
Construction Contract | 199,998 | 210,567 |
Other Construction | 0 | 0 |
Total Construction | 229,998 | 239,486 |
Funding Increase | 51,633 | |
Funding Surplus | - 53,809 | |
Total TIB Funding | 257,822 | 271,392 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MOXEE | 13,570 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 13,570 | 5.0% |
Project Description
This project will complete a grind and overlay. ADA ramps will be updated on Moxee Ave as needed.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |