City of Mabton's FY 2021 Overlay Project

2-E-942(004)-1

2-E-942(004)-1
FY 2021 Overlay Project

Multiple Locations

FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $323,000

County: Yakima   |   Legislative District: 15   |   Project Length: 0.34   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 08/15/2022

Project Information

Lead Agency MABTON
Funding Year 2021
Program SCPP
Current Phase Audit
Legislative District 15
Congressional District 4
Federal Route Number L390
Project Length 0.34 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Laura Vazquez
Contact Email Laura.vazquez@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 08/15/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2019
Delayed Project Date 07/01/2022  
Predesign Approval
Design Approval 02/01/2020 01/21/2020
Bid Auth. Approval 03/26/2021 03/24/2021
Construction Approval 04/16/2021 04/26/2021
Project Closeout 04/30/2022 08/05/2022
Audit Date   08/15/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 37,600 37,600
Right of Way 0 0
Total Design 37,600 37,600
     
Construction Engineering 37,600 37,600
Construction Contract 251,240 247,799
Other Construction 0 0
Total Construction 288,840 285,399
     
Funding Surplus - 3,440  
Total TIB Funding 323,000 322,999

Local Funding Partners

Funding Amount Percent
MABTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Mill existing 11-foot travel lanes to a depth of 2-inches and inlay the roadway. Subgrade repair will be included in areas determined necessary. Many of the curb ramps in this segment have recently been upgraded. Upgrading these 2 ramps will complete the work on this segment to provide ADA compliant pedestrian facilities.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.