The pavement condition rating for Washington Street - 1st Ave to 6th Ave 46.
Projects — TIB Project Information
TIB Project Information
City of Mabton's FY 2021 Overlay Project
2-E-942(004)-1
2-E-942(004)-1
FY 2021 Overlay Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $323,000
County: Yakima | Legislative District: 15 | Project Length: 0.34 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/15/2022
Project Information
Lead Agency | MABTON |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | L390 |
Project Length | 0.34 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Laura Vazquez |
Contact Email | Laura.vazquez@co.yakima.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/15/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 01/21/2020 |
Bid Auth. Approval | 03/26/2021 | 03/24/2021 |
Construction Approval | 04/16/2021 | 04/26/2021 |
Project Closeout | 04/30/2022 | 08/05/2022 |
Audit Date | 08/15/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 37,600 | 37,600 |
Right of Way | 0 | 0 |
Total Design | 37,600 | 37,600 |
Construction Engineering | 37,600 | 37,600 |
Construction Contract | 251,240 | 247,799 |
Other Construction | 0 | 0 |
Total Construction | 288,840 | 285,399 |
Funding Surplus | - 3,440 | |
Total TIB Funding | 323,000 | 322,999 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MABTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Mill existing 11-foot travel lanes to a depth of 2-inches and inlay the roadway. Subgrade repair will be included in areas determined necessary. Many of the curb ramps in this segment have recently been upgraded. Upgrading these 2 ramps will complete the work on this segment to provide ADA compliant pedestrian facilities.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |