Projects — TIB Project Information
TIB Project Information
City of Goldendale's FY 2018 Overlay Project
2-E-935(003)-1
2-E-935(003)-1
FY 2018 Overlay Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $353,782
County: Klickitat | Legislative District: 14 | Project Length: 0.65 | TIB Engineer: Jonathan Heusman | Last Payment Date: 06/25/2018
Project Information
Lead Agency | GOLDENDALE |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 14 |
Congressional District | 3 |
Federal Route Number | L201 |
Project Length | 0.65 mi. |
ADT | 750 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Karl Enyeart, PE |
Contact Email | kenyeart@ci.goldendale.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 06/25/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/12/2016 |
Bid Auth. Approval | 04/01/2017 | 05/31/2017 |
Construction Approval | 03/15/2018 | 03/12/2018 |
Project Closeout | 12/31/2018 | 06/18/2018 |
Audit Date | 06/25/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 8,786 | 24,882 |
Right of Way | 0 | 0 |
Total Design | 8,786 | 24,882 |
Construction Engineering | 8,786 | 23,802 |
Construction Contract | 278,280 | 456,424 |
Other Construction | 0 | 0 |
Total Construction | 287,066 | 480,226 |
Funding Increase | 57,930 | |
Total TIB Funding | 353,782 | 505,108 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GOLDENDALE | 151,326 | 30.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 151,326 | 22.4% |
Project Description
This project will provide a 3' grind and overlay on the northbound and southbound lanes of South Columbus Avenue. The center turn lane will have a fog seal to refresh the color and provide the project with an improved finish. The sewer line will be replaced prior to overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |