Town of Starbuck's FY 2012 Overlay Project
2-E-925(002)-1
2-E-925(002)-1
FY 2012 Overlay Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $97,133
County: Columbia | Legislative District: 16 | Project Length: 0.52 | TIB Engineer: Jonathan Heusman | Last Payment Date: 03/01/2013
Project Information
Lead Agency | STARBUCK |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.52 mi. |
ADT | 125 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Darcy Linklater |
Contact Email | dlinklater@starbuckwa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 03/01/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 12/15/2010 | 12/21/2010 |
Bid Auth. Approval | 06/01/2011 | 12/21/2010 |
Construction Approval | 07/01/2012 | 06/14/2012 |
Project Closeout | 02/01/2013 | 02/12/2013 |
Audit Date | 03/04/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 8,556 | 4,162 |
Right of Way | 0 | 0 |
Total Design | 8,556 | 4,162 |
Construction Engineering | 8,556 | 3,918 |
Construction Contract | 83,371 | 87,385 |
Other Construction | 0 | 1,667 |
Total Construction | 91,927 | 92,970 |
Funding Increase | 10,677 | |
Funding Surplus | - 14,027 | |
Total TIB Funding | 97,133 | 97,132 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
STARBUCK | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will repair areas of base failure with digouts and overlay portions of Front Street, Baxter Street, McNeil Street, First Street and Second Street with a 2-inch overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |