Projects — TIB Project Information
TIB Project Information
City of Dayton's FY 2022 Overlay Project
2-E-924(008)-1
2-E-924(008)-1
FY 2022 Overlay Project
Multiple Locations
FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $457,388
County: Columbia | Legislative District: 16 | Project Length: 0.44 | TIB Engineer: Jonathan Heusman | Last Payment Date: 05/15/2024
Project Information
Lead Agency | DAYTON |
Funding Year | 2022 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.44 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Deb Hays |
Contact Email | dhays@daytonwa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 05/15/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 01/14/2021 |
Bid Auth. Approval | 02/28/2023 | 03/13/2023 |
Construction Approval | 04/30/2023 | 05/19/2023 |
Project Closeout | 05/28/2024 | 05/08/2024 |
Audit Date | 05/15/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 27,900 | 31,000 |
Right of Way | 0 | 0 |
Total Design | 27,900 | 31,000 |
Construction Engineering | 27,900 | 18,598 |
Construction Contract | 244,980 | 478,610 |
Other Construction | 0 | 0 |
Total Construction | 272,880 | 497,208 |
Funding Increase | 156,608 | |
Total TIB Funding | 457,388 | 528,208 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAYTON | 70,821 | 13.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 70,821 | 13.4% |
Project Description
2-inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |