The current PCR of Cameron Street is a 41 where they plan to complete pavement repair and a 59 on the eastern portion of Cameron
Projects — TIB Project Information
TIB Project Information
City of Dayton's FY 2021 Seal Coat Project
2-E-924(007)-1
2-E-924(007)-1
FY 2021 Seal Coat Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $104,771
County: Columbia | Legislative District: 16 | Project Length: 0.58 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/06/2021
Project Information
Lead Agency | DAYTON |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.58 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Trina Cole |
Contact Email | tcole@daytonwa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/06/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 01/21/2020 |
Bid Auth. Approval | 05/01/2021 | 03/04/2021 |
Construction Approval | 04/15/2021 | 04/15/2021 |
Project Closeout | 11/26/2021 | 11/15/2021 |
Audit Date | 12/06/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 2,850 | 5,893 |
Right of Way | 0 | 0 |
Total Design | 2,850 | 5,893 |
Construction Engineering | 2,850 | 1,369 |
Construction Contract | 115,900 | 75,995 |
Other Construction | 0 | 28,968 |
Total Construction | 118,750 | 106,332 |
Funding Increase | 0 | |
Funding Surplus | - 16,829 | |
Total TIB Funding | 104,771 | 112,225 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAYTON | 7,454 | 6.6% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 7,454 | 6.6% |
Project Description
The work includes pavement repair near the intersection with US 12, crack sealing, preleveling, chip seal, fog seal, and striping. Cameron Street is an important industrial collector in the City of Dayton that also serves the Boys and Girls Club, Port of Columbia, Dayton School District sports fields, and the Columbia County Transfer Station. The street experiences high traffic and is in need of preservation to maintain satisfactory pavement conditions and prevent future failure.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |