City of Dayton's FY 2017 Overlay Project
2-E-924(004)-1
2-E-924(004)-1
FY 2017 Overlay Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $257,962
County: Columbia | Legislative District: 16 | Project Length: 0.31 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/29/2016
Project Information
Lead Agency | DAYTON |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.31 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Trina Cole |
Contact Email | cityclerk@daytonwa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/29/2016 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 12/28/2015 |
Bid Auth. Approval | 02/28/2016 | 04/21/2016 |
Construction Approval | 05/01/2016 | 05/24/2016 |
Project Closeout | 10/31/2016 | 11/22/2016 |
Audit Date | 11/29/2016 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 24,180 | 26,000 |
Right of Way | 0 | 0 |
Total Design | 24,180 | 26,000 |
Construction Engineering | 26,040 | 27,722 |
Construction Contract | 212,040 | 223,657 |
Other Construction | 0 | 0 |
Total Construction | 238,080 | 251,379 |
Funding Increase | 5,831 | |
Funding Surplus | - 10,129 | |
Total TIB Funding | 257,962 | 277,379 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAYTON | 19,417 | 7.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 19,417 | 0.0% |
Project Description
This project prelevels, upgrades 11 ADA ramps and provides a 2-inch overlay of Front Street between W Main Street and E Dayton Avenue.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |