 Projects — TIB Project Information

TIB Project Information

Town of Northport's FY 2019 Seal Coat Project

2-E-905(002)-1

2-E-905(002)-1
FY 2019 Seal Coat Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $100,142

County: Stevens   |   Legislative District: 7   |   Project Length: 0.40   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 08/01/2019

Project Information

Lead Agency NORTHPORT
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 0.40 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Karen Baribault
Contact Email townofnorthport@plix.com
TIB Engineer Andrew Beagle
Last Payment Date 08/01/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 02/06/2018
Bid Auth. Approval 04/01/2018 02/06/2018
Construction Approval 06/01/2018 06/14/2018
Project Closeout 09/01/2019 06/25/2019
Audit Date   08/01/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 12,000 0
Total Design 12,000 0
     
Construction Engineering 0 0
Construction Contract 110,146 100,142
Other Construction 0 0
Total Construction 110,146 100,142
     
Funding Surplus - 22,004  
Total TIB Funding 100,142 100,142

Local Funding Partners

Funding Amount Percent
NORTHPORT 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project repairs pavement, seals cracks and chip seals the following South Avenue - 10th to 4th

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments