The existing roadway surfaces are worn bituminous surface treatment with some cracking and ravelling. The routes serve the school complex, health clinic and central business district.
Projects — TIB Project Information
TIB Project Information
Town of Northport's FY 2009 Seal Coat Project
2-E-905(001)-1
2-E-905(001)-1
FY 2009 Seal Coat Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $55,348
County: Stevens | Legislative District: 7 | Project Length: 1.61 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/16/2009
Project Information
Lead Agency | NORTHPORT |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.61 mi. |
ADT | 200 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Jerry Matteson |
Contact Email | northprt@theofficenet.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/16/2009 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/01/2008 | 07/31/2008 |
Bid Auth. Approval | 01/01/2008 | 07/31/2008 |
Construction Approval | 08/01/2009 | 08/01/2009 |
Project Closeout | 12/31/2009 | 10/15/2009 |
Audit Date | 11/16/2009 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 50,348 | 60,437 |
Other Construction | 0 | 0 |
Total Construction | 50,348 | 60,437 |
Funding Increase | 5,000 | |
Total TIB Funding | 55,348 | 60,437 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NORTHPORT | 5,089 | 10.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 5,089 | 10.1% |
Project Description
Chip Seal the following segments 2nd Street - Center Avenue to Summit Ave 6th Street - Summit Avenue to South Ave 7th Street - Leroy Avenue to Summit Ave 8th Street - Columbia Avenue to Leroy Ave Columbia Avenue - 8th Street to 4th Street Leroy Avenue - 10th Street to Fir Avenue Silver Crown Avenue - 10th Street to 7th Street Summit Avenue - 7th Street to 5th Street
Existing Condition
Project Benefits
- Extend road life;
- Lower maintenance costs
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |