Projects — TIB Project Information
TIB Project Information
City of Colville's 2017 Emergency Pavement Repair Project
2-E-902(001)-1
2-E-902(001)-1
2017 Emergency Pavement Repair Project
Various Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $37,331
County: Stevens | Legislative District: 7 | Project Length: 0.10 | TIB Engineer: Andrew Beagle | Last Payment Date: 08/30/2017
Project Information
Lead Agency | COLVILLE |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Ron Frostad |
Contact Email | ronf@colville.wa.us |
TIB Engineer | Andrew Beagle |
Last Payment Date | 08/30/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 05/12/2017 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 06/15/2017 | 06/27/2017 |
Bid Auth. Approval | 06/15/2017 | 06/27/2017 |
Construction Approval | 06/15/2017 | 06/27/2017 |
Project Closeout | 08/31/2017 | 08/29/2017 |
Audit Date | 08/30/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 37,326 | 39,295 |
Other Construction | 0 | 0 |
Total Construction | 37,326 | 39,295 |
Funding Increase | 5 | |
Total TIB Funding | 37,331 | 39,295 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COLVILLE | 1,964 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,964 | 5.0% |
Project Description
See Approved Scope
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |