Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Chewelah's 2017 Emergency Pavement Repair Project

2-E-901(002)-1

2-E-901(002)-1
2017 Emergency Pavement Repair Project

Various Locations

FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $29,785

County: Stevens   |   Legislative District: 7   |   Project Length: 0.10   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/13/2017

Project Information

Lead Agency CHEWELAH
Funding Year 2018
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Local Access
Type of Work Resurfacing
Project Contact Mike Frizzell
Contact Email mfrizzell@cityofchewelah.org
TIB Engineer Andrew Beagle
Last Payment Date 11/13/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   06/01/2017
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 06/15/2017 06/27/2017
Bid Auth. Approval 06/15/2017 06/27/2017
Construction Approval 06/15/2017 06/27/2017
Project Closeout 08/31/2017 10/31/2017
Audit Date   11/13/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 35,055 31,353
Other Construction 0 0
Total Construction 35,055 31,353
     
Funding Surplus - 5,270  
Total TIB Funding 29,785 31,353

Local Funding Partners

Funding Amount Percent
CHEWELAH 1,568 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,568 5.0%

Project Description

See Approved Scope

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments