TIB Project Information

City of Chewelah's FY 2015 Overlay Project

2-E-901(001)-1

2-E-901(001)-1
FY 2015 Overlay Project

Multiple Locations

FY 2015 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $120,648

County: Stevens   |   Legislative District: 7   |   Project Length: 0.27   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 03/02/2015

Project Information

Lead Agency CHEWELAH
Funding Year 2015
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 0.27 mi.
ADT 0
Functional Class Local Access
Type of Work Resurfacing
Project Contact Mike Frizzell
Contact Email mfrizzell@cityofchewelah.org
TIB Engineer Andrew Beagle
Last Payment Date 03/02/2015

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2013
Delayed Project Date 07/01/2016  
Predesign Approval
Design Approval 01/01/2014 01/08/2014
Bid Auth. Approval 06/01/2014 06/05/2014
Construction Approval 07/01/2014 07/09/2014
Project Closeout 02/01/2015 02/18/2015
Audit Date   03/02/2015
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 9,028 9,493
Right of Way 0 0
Total Design 9,028 9,493
     
Construction Engineering 8,075 7,277
Construction Contract 89,790 110,228
Other Construction 0 0
Total Construction 97,865 117,505
     
Funding Increase 13,755  
Total TIB Funding 120,648 126,997

Local Funding Partners

Funding Amount Percent
CHEWELAH 6,349 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 6,349 5.0%

Project Description

The project seals cracks, repairs pavement and provides a two inch overlay on King Street between Stevens Street and rail crossing west of SR 395. The scope includes upgrade of ADA ramps to the current standard and replacement of non-adjustable catch basin grates.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments