Surfaces on the following segments are showing some deterioration and wear PCR 59 - Commercial Ave - 1st St to Waverly Rd PCR 59 - Riverside Ave - Prairie View Rd to Elm St
Projects — TIB Project Information
TIB Project Information
Town of Waverly's FY 2017 Seal Coat Project
2-E-900(001)-1
2-E-900(001)-1
FY 2017 Seal Coat Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $26,339
County: Spokane | Legislative District: 9 | Project Length: 0.40 | TIB Engineer: Andrew Beagle | Last Payment Date: 02/18/2020
Project Information
Lead Agency | WAVERLY |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.40 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Kynda Browning |
Contact Email | waverlytown@palousenet.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 02/18/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 04/21/2016 |
Bid Auth. Approval | 04/01/2016 | 04/21/2016 |
Construction Approval | 05/01/2016 | 04/21/2016 |
Project Closeout | 04/01/2019 | 02/05/2020 |
Audit Date | 02/18/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 5,000 | 0 |
Right of Way | 0 | 0 |
Total Design | 5,000 | 0 |
Construction Engineering | 0 | 3,715 |
Construction Contract | 45,025 | 22,624 |
Other Construction | 0 | 0 |
Total Construction | 45,025 | 26,339 |
Funding Surplus | - 23,686 | |
Total TIB Funding | 26,339 | 26,339 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WAVERLY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project repairs pavement, seals cracks and chip seals the segments.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |