City of Soap Lake's FY 2015 Overlay Project
2-E-865(008)-1
2-E-865(008)-1
FY 2015 Overlay Project
Multiple Locations
FY 2015 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $297,472
County: Grant | Legislative District: 12 | Project Length: 0.13 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/30/2015
Project Information
Lead Agency | SOAP LAKE |
Funding Year | 2015 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.13 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Karen Dillion |
Contact Email | sladmin@smwireless.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | 09/30/2015 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2016 | |
Predesign Approval | ||
Design Approval | 01/01/2014 | 12/31/2013 |
Bid Auth. Approval | 03/15/2014 | 03/05/2014 |
Construction Approval | 04/01/2014 | 04/07/2014 |
Project Closeout | 03/31/2015 | 09/21/2015 |
Audit Date | 09/30/2015 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 29,900 | 29,900 |
Right of Way | 0 | 0 |
Total Design | 29,900 | 29,900 |
Construction Engineering | 29,900 | 30,628 |
Construction Contract | 200,100 | 236,944 |
Other Construction | 0 | 0 |
Total Construction | 230,000 | 267,572 |
Funding Increase | 37,572 | |
Total TIB Funding | 297,472 | 297,472 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SOAP LAKE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Repair pavement and overlay streets replace existing sidewalk, curb & gutter upgrade ramps on 1st Avenue.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |