City of Republic's FY 2009 Overlay Project

2-E-855(001)-1

2-E-855(001)-1
FY 2009 Overlay Project

Multiple Locations

FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $142,532

County: Ferry   |   Legislative District: 7   |   Project Length: 0.54   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 07/02/2009

Project Information

Lead Agency REPUBLIC
Funding Year 2009
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 0.54 mi.
ADT 250
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Linda Hall
Contact Email rcouncil@rcabletv.com
TIB Engineer Andrew Beagle
Last Payment Date 07/02/2009

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2007
Delayed Project Date 07/01/2010  
Predesign Approval
Design Approval 01/01/2008 01/24/2008
Bid Auth. Approval 01/01/2008 01/24/2008
Construction Approval 02/01/2009 01/05/2009
Project Closeout 07/01/2009 06/29/2009
Audit Date   07/02/2009
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 94,000 142,532
Other Construction 0 0
Total Construction 94,000 142,532
     
Funding Increase 48,532  
Total TIB Funding 142,532 142,532

Local Funding Partners

Funding Amount Percent
REPUBLIC 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The project consists of a 2 inch overlay of the following segments 8th Street - Kean Street to Clark Avenue Delaware Avenue - Kean Street to Clark Avenue Kauffman Street - Eureka Avenue to SR 20 Kean Street - Delaware Avenue to SR 20 Portland Street - Klondike Road to Keller Street

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments