The pavement condition rating of Foster Avenue - 10th St to 14th St 60
Projects — TIB Project Information
TIB Project Information
City of Bridgeport's FY 2022 Overlay Project
2-E-851(006)-1
2-E-851(006)-1
FY 2022 Overlay Project
Multiple Locations
FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $226,922
County: Douglas | Legislative District: 12 | Project Length: 0.28 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/01/2021
Project Information
Lead Agency | BRIDGEPORT |
Funding Year | 2022 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.28 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Stuart Dezellum |
Contact Email | pwsuper@nwi.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/01/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/10/2020 |
Bid Auth. Approval | 04/01/2021 | 05/20/2021 |
Construction Approval | 06/30/2021 | 06/14/2021 |
Project Closeout | 10/31/2021 | 10/29/2021 |
Audit Date | 11/01/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 25,744 | 17,410 |
Right of Way | 0 | 0 |
Total Design | 25,744 | 17,410 |
Construction Engineering | 25,744 | 25,397 |
Construction Contract | 172,179 | 196,069 |
Other Construction | 0 | 0 |
Total Construction | 197,923 | 221,466 |
Funding Increase | 13,062 | |
Funding Surplus | - 9,807 | |
Total TIB Funding | 226,922 | 238,876 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BRIDGEPORT | 11,955 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 11,955 | 5.0% |
Project Description
Overlay the existing roadway, with subgrade repair (digouts) where necessary. Recent completed work on Foster Avenue between 14th Ave and 17th Ave showed that the roadway lacks a gravel base and the HMA is less than 2 inches thick, so transition planning to connect to side streets would not provide a suitable base for paving. Instead of transition paving, subgrade repair consisting of 6-inches of crushed surfacing top course and 2-inches of HMA will be provided to connect to side streets.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |