Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Leavenworth's Pavement Pilot Project

2-E-850(004)-1

2-E-850(004)-1
Pavement Pilot Project

Whitman Street

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $81,589

County: Chelan   |   Legislative District: 12   |   Project Length: 0.14   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 12/01/2020

Project Information

Lead Agency LEAVENWORTH
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 8
Federal Route Number 9999
Project Length 0.14 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Herb Amick
Contact Email herba@cityofleavenworth.com
TIB Engineer Andrew Beagle
Last Payment Date 12/01/2020

Project Schedule

  Target Date Actual Date
Project Selection Date   02/18/2020
Delayed Project Date 07/01/2022  
Predesign Approval
Design Approval 03/15/2020 03/17/2020
Bid Auth. Approval 06/01/2020 07/06/2020
Construction Approval 07/24/2020 07/30/2020
Project Closeout 10/31/2020 11/25/2020
Audit Date   12/01/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 313
Right of Way 0 0
Total Design 0 313
     
Construction Engineering 0 0
Construction Contract 285,000 88,475
Other Construction 0 0
Total Construction 285,000 88,475
     
Funding Surplus - 203,411  
Total TIB Funding 81,589 88,788

Local Funding Partners

Funding Amount Percent
LEAVENWORTH 7,199 8.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 7,199 8.1%

Project Description

Assess low volume streets for low cost treatments.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.