Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Leavenworth's 2017 Emergency Pavement Repair Project

2-E-850(003)-1

2-E-850(003)-1
2017 Emergency Pavement Repair Project

Various Locations

FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $37,145

County: Chelan   |   Legislative District: 12   |   Project Length: 0.10   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 10/13/2017

Project Information

Lead Agency LEAVENWORTH
Funding Year 2018
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 8
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Herb Amick
Contact Email herba@cityofleavenworth.com
TIB Engineer Andrew Beagle
Last Payment Date 10/13/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   06/01/2017
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 07/01/2017 06/27/2017
Bid Auth. Approval 07/01/2017 06/27/2017
Construction Approval 07/01/2017 06/27/2017
Project Closeout 08/31/2017 09/29/2017
Audit Date   10/13/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 50,000 39,100
Other Construction 0 0
Total Construction 50,000 39,100
     
Funding Surplus - 12,855  
Total TIB Funding 37,145 39,100

Local Funding Partners

Funding Amount Percent
LEAVENWORTH 1,955 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,955 31.9%

Project Description

See Approved Scope

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments