The segment selected for overlay is Pioneer Way - Evergreen to School Lane The current pavement condition rating (PCR) is 52.
Projects — TIB Project Information
TIB Project Information
City of Cashmere's FY 2014 Red Town Project
2-E-847(002)-1
2-E-847(002)-1
FY 2014 Red Town Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $364,523
County: Chelan | Legislative District: 12 | Project Length: 0.71 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/15/2014
Project Information
Lead Agency | CASHMERE |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | G042 |
Project Length | 0.71 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Mark Botello |
Contact Email | mark@cityofcashmere.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/15/2014 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 01/16/2013 |
Bid Auth. Approval | 06/01/2013 | 04/19/2013 |
Construction Approval | 07/01/2013 | 05/13/2013 |
Project Closeout | 12/31/2013 | 01/09/2014 |
Audit Date | 01/15/2014 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 32,500 | 27,807 |
Right of Way | 0 | 0 |
Total Design | 32,500 | 27,807 |
Construction Engineering | 32,500 | 25,119 |
Construction Contract | 260,000 | 330,782 |
Other Construction | 0 | 0 |
Total Construction | 292,500 | 355,901 |
Funding Increase | 44,579 | |
Funding Surplus | - 5,056 | |
Total TIB Funding | 364,523 | 383,709 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CASHMERE | 19,185 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 19,185 | 5.0% |
Project Description
The project provides pavement, planning hot mix asphalt overlay, curb, gutter and sidewalk upgrades and striping on Pioneer Avenue between Evergreen Street and Division Street.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |