The existing surfaces are cracked, extensively on Tichenal Road. Both routes serve industry, commercial and tourist destinations.
Projects — TIB Project Information
TIB Project Information
City of Cashmere's FY 2009 Overlay Project
2-E-847(001)-1
2-E-847(001)-1
FY 2009 Overlay Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $105,605
County: Chelan | Legislative District: 12 | Project Length: 0.25 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/01/2009
Project Information
Lead Agency | CASHMERE |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | F043 |
Project Length | 0.25 mi. |
ADT | 500 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Mark Botello |
Contact Email | mark@cityofcashmere.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/01/2009 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/01/2008 | 02/26/2008 |
Bid Auth. Approval | 01/01/2008 | 02/26/2008 |
Construction Approval | 02/01/2009 | 10/07/2008 |
Project Closeout | 10/31/2009 | 11/16/2009 |
Audit Date | 12/01/2009 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 8,270 |
Right of Way | 0 | 0 |
Total Design | 0 | 8,270 |
Construction Engineering | 0 | 6,062 |
Construction Contract | 68,886 | 101,017 |
Other Construction | 0 | 0 |
Total Construction | 68,886 | 107,079 |
Funding Increase | 36,719 | |
Total TIB Funding | 105,605 | 115,349 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CASHMERE | 9,744 | 8.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 9,744 | 8.4% |
Project Description
Grind, Prelevel and 2 inch overlay Cotlet Way - Wenatchee River Bridge to Titchenal Road Titchenal Road - Cotlet Way to Titchenal Road
Existing Condition
Project Benefits
- Avert reconstruction;
- Improve access
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |