Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Ritzville's 2022 Crack Seal

2-E-845(008)-1

2-E-845(008)-1
2022 Crack Seal

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $122,875

County: Adams   |   Legislative District: 9   |   Project Length: 8.90   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 07/17/2023

Project Information

Lead Agency RITZVILLE
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 8.90 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Scott Yaeger
Contact Email scotty@co.adams.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 07/17/2023

Project Schedule

  Target Date Actual Date
Project Selection Date   03/28/2023
Delayed Project Date 07/01/2025  
Predesign Approval 03/23/2023
Design Approval 04/30/2023 04/10/2023
Bid Auth. Approval 04/30/2023 04/30/2023
Construction Approval 04/30/2023 04/10/2023
Project Closeout 10/31/2023 07/05/2023
Audit Date   07/17/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 79,378 129,342
Other Construction 0 0
Total Construction 79,378 129,342
     
Funding Increase 43,497  
Total TIB Funding 122,875 129,342

Local Funding Partners

Funding Amount Percent
RITZVILLE 6,467 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 6,467 5.0%

Project Description

Crack Seal Large portion of City Streets.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.