City of Ritzville's FY 2018 Rehabilitation Project
2-E-845(005)-1
2-E-845(005)-1
FY 2018 Rehabilitation Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $318,967
County: Adams | Legislative District: 9 | Project Length: 0.26 | TIB Engineer: Jonathan Heusman | Last Payment Date: 09/04/2018
Project Information
Lead Agency | RITZVILLE |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.26 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Larry Swift |
Contact Email | larry.swift@ritzville-wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 09/04/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 01/26/2017 |
Bid Auth. Approval | 03/01/2018 | 02/26/2018 |
Construction Approval | 03/15/2018 | 03/27/2018 |
Project Closeout | 10/31/2018 | 08/28/2018 |
Audit Date | 09/04/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 42,750 | 44,248 |
Right of Way | 0 | 0 |
Total Design | 42,750 | 44,248 |
Construction Engineering | 28,500 | 42,550 |
Construction Contract | 280,345 | 264,113 |
Other Construction | 0 | 0 |
Total Construction | 308,845 | 306,663 |
Funding Surplus | - 32,628 | |
Total TIB Funding | 318,967 | 350,911 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RITZVILLE | 31,944 | 9.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 31,944 | 5.0% |
Project Description
This project will pulverize and apply a cement treated base to 1st Street between Cascade St and the North City Limits
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |