City of Ritzville's FY 2018 Rehabilitation Project

2-E-845(005)-1

2-E-845(005)-1
FY 2018 Rehabilitation Project

Multiple Locations

FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $318,967

County: Adams   |   Legislative District: 9   |   Project Length: 0.26   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/04/2018

Project Information

Lead Agency RITZVILLE
Funding Year 2018
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.26 mi.
ADT 250
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Larry Swift
Contact Email larry.swift@ritzville-wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 09/04/2018

Project Schedule

  Target Date Actual Date
Project Selection Date   11/18/2016
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 01/01/2017 01/26/2017
Bid Auth. Approval 03/01/2018 02/26/2018
Construction Approval 03/15/2018 03/27/2018
Project Closeout 10/31/2018 08/28/2018
Audit Date   09/04/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 42,750 44,248
Right of Way 0 0
Total Design 42,750 44,248
     
Construction Engineering 28,500 42,550
Construction Contract 280,345 264,113
Other Construction 0 0
Total Construction 308,845 306,663
     
Funding Surplus - 32,628  
Total TIB Funding 318,967 350,911

Local Funding Partners

Funding Amount Percent
RITZVILLE 31,944 9.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 31,944 5.0%

Project Description

This project will pulverize and apply a cement treated base to 1st Street between Cascade St and the North City Limits

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments