City of Ritzville's FY 2017 Overlay Project

2-E-845(004)-1

2-E-845(004)-1
FY 2017 Overlay Project

Multiple Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $175,908

County: Adams   |   Legislative District: 9   |   Project Length: 0.13   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 02/15/2017

Project Information

Lead Agency RITZVILLE
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 4
Federal Route Number M011
Project Length 0.13 mi.
ADT 350
Functional Class Collector
Type of Work Resurfacing
Project Contact Larry Swift
Contact Email larry.swift@ritzville-wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 02/15/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2015
Delayed Project Date 07/01/2018  
Predesign Approval
Design Approval 01/15/2016 01/11/2016
Bid Auth. Approval 04/01/2016 04/26/2016
Construction Approval 06/01/2016 05/23/2016
Project Closeout 12/31/2016 02/07/2017
Audit Date   02/15/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 21,923 15,623
Right of Way 0 0
Total Design 21,923 15,623
     
Construction Engineering 21,923 16,681
Construction Contract 146,154 157,565
Other Construction 0 0
Total Construction 168,077 174,246
     
Funding Increase 1,982  
Funding Surplus - 16,074  
Total TIB Funding 175,908 189,869

Local Funding Partners

Funding Amount Percent
RITZVILLE 13,961 7.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 13,961 7.4%

Project Description

This project will grind off the existing 2' of HMA and replace it with a thicker 4' section over the existing 9-12' of base course and geogrid already in place. In addition, upgrades 5 ADA ramps.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.