Projects — TIB Project Information
TIB Project Information
City of Ritzville's FY 2014 Overlay Project
2-E-845(003)-1
2-E-845(003)-1
FY 2014 Overlay Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $233,138
County: Adams | Legislative District: 9 | Project Length: 0.26 | TIB Engineer: Jonathan Heusman | Last Payment Date: 09/30/2015
Project Information
Lead Agency | RITZVILLE |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 4 |
Federal Route Number | M011 |
Project Length | 0.26 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Larry Swift |
Contact Email | larry.swift@ritzville-wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 09/30/2015 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 02/01/2013 | 01/17/2013 |
Bid Auth. Approval | 06/01/2014 | 07/09/2014 |
Construction Approval | 08/01/2014 | 08/20/2014 |
Project Closeout | 02/28/2015 | 09/01/2015 |
Audit Date | 09/30/2015 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 13,333 | 17,763 |
Right of Way | 0 | 0 |
Total Design | 13,333 | 17,763 |
Construction Engineering | 6,666 | 28,782 |
Construction Contract | 100,001 | 203,304 |
Other Construction | 5,000 | 0 |
Total Construction | 111,667 | 232,086 |
Funding Increase | 108,138 | |
Total TIB Funding | 233,138 | 249,849 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RITZVILLE | 16,711 | 6.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 16,711 | 6.7% |
Project Description
Grind, overlay and upgrade ADA ramps on Division Street from 1st Ave to 6th Ave.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |