Town of Lind's 2023 Crack Seal
2-E-843(002)-1
2-E-843(002)-1
2023 Crack Seal
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $6,936
County: Adams | Legislative District: 9 | Project Length: 1.25 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/14/2023
Project Information
Lead Agency | LIND |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.25 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Paula Bell |
Contact Email | mayorbell.lind@gmail.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/14/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 07/31/2023 | |
Delayed Project Date | 07/01/2026 | |
Predesign Approval | ||
Design Approval | 08/01/2023 | 07/31/2023 |
Bid Auth. Approval | 08/04/2023 | 08/01/2023 |
Construction Approval | 08/04/2023 | 08/01/2023 |
Project Closeout | 08/11/2023 | 08/09/2023 |
Audit Date | 08/14/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 6,936 | 7,707 |
Other Construction | 0 | 0 |
Total Construction | 6,936 | 7,707 |
Total TIB Funding | 6,936 | 7,707 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LIND | 771 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 771 | 10.0% |
Project Description
Crack Seal about 20 blocks.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |