Town of Lind's FY 2019 Rehabilitation Project

2-E-843(001)-2

2-E-843(001)-2
FY 2019 Rehabilitation Project

2018 Construction Phase

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $42,722

County: Adams   |   Legislative District: 9   |   Project Length: 0.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 10/30/2018

Project Information

Lead Agency LIND
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Jamie Schmunk
Contact Email townoflind@sosmail.us
TIB Engineer Jonathan Heusman
Last Payment Date 10/30/2018

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 12/11/2017
Bid Auth. Approval 02/28/2018 02/13/2018
Construction Approval 03/31/2018 03/27/2018
Project Closeout 10/31/2018 09/24/2018
Audit Date   10/30/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 6,150 30,720
Construction Contract 58,012 311,056
Other Construction 0 0
Total Construction 64,162 341,776
     
Funding Surplus - 21,440  
Total TIB Funding 42,722 341,776

Local Funding Partners

Funding Amount Percent
LIND 0 0.0%
WSDOT Funding 0 0.0%
FEMA  299,054 87.5%
 
 
 
 
 
 
 
Total Local Funding 299,054 87.5%

Project Description

This project is a FEMA match project. The project will fix roads that deteriorated during the winter of 2017.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.