Projects — TIB Funding Cycles
FY 2023 UAP Selections
|
|
||||
Region: Puget Sound | Legislative District: 30 | Length: 0.45 mi. | FY 2023 Urban Arterial Program (UAP) |
Existing ConditionsThis section of SR 99 has had an unusally high number of severe collisions, including 7 fatalities over the last 10 years (3 just in June 2021). Excessive speed for conditions and lack of access management and turn lanes have been contributing factors to this collision history. In addition, congestion in Fife and Puyallup have increased volumes and the intersection of S 373rd Street at SR 99 is forecast to have a failing level of service. In addition, a planned warehouse in Milton will exacerbate this condition. The City is working with this developer to provide mitigation funds for this project. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 298,408 | 151,592 | 450,000 |
Right of Way | 298,408 | 151,592 | 450,000 |
Construction | 1,903,184 | 966,816 | 2,870,000 |
Project Totals | $2,500,000 | $1,270,000 | $3,770,000 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
66.3% | 33.7% | 20% |
Summary of Improvements
- The project benefits the local community by providing safer access to side streets, reducing delay on side streets. Through traffic on SR 99 would benefit from the reduced risk of collisions with minimal additional delay. WSDOT and the City would benefit from reduced tort liability risk.
Description of Improvements
The City will establish median control throughout the length of the project to reduce the severity of collisions from driveways and side streets, and construct a roundabout at the intersection of S 373rd Street to address the forecast level of service failure, to accommodate additional development from Milton, and assist in managing speeds on SR 99.