Projects — TIB Funding Cycles
FY 2023 SP Selections
|
|
||||
Region: East | Legislative District: 15 | Length: 3,400.00 ft. | FY 2023 Sidewalk Program (SP) |
Existing ConditionsThe Valleyview Avenue, Third Street, and Southern Avenue improvement project is proposed for the 3,300 LF section on Valleyview Avenue (1st Street to 3rd Street), South Third Street (Valleyview Avenue to Southern Avenue), and Southern Avenue (3rd Street to 1st Street). The existing roadway is only 22 feet wide for a majority of its length with very limited curb and gutter, no sidewalk, limited street lighting, and no storm drainage facilities. This route is a designated bike and walking route. School buses drop off and pick up a large amount of children at the corner of Third Street and Pleasant Avenue. With no sidewalks along the roadway, the children unsafely walk on the edge of the travel lanes. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 0 | 0 |
Right of Way | 0 | 0 | 0 |
Construction | 400,000 | 663,850 | 1,063,850 |
Project Totals | $400,000 | $663,850 | $1,063,850 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
37.6% | 62.4% | 10% |
Summary of Improvements
- Improves pedestrian safety;
- Completes gap;
- Removes ADA barriers
Description of Improvements
Reconstruction of Valleyview Avenue, Third Street, and Southern Avenue to a 28-foot wide, two-lane roadways. The project will include curb and gutters, sidewalks, intersection curb ramps, storm drainage facilities, and illumination system.