Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Funding Cycles

FY 2024 SCPP Selections

Town of South Cle Elum
2022 Seal Coat Award
Multiple Locations
TIB Award Amount
$29,136
Region: East   |   Legislative District: 13   |   Length: 0.00 mi. FY 2024 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 1,500 0 1,500
Right of Way 0 0 0
Construction 27,636 0 27,636
Project Totals $29,136 $0 $29,136

Local Match

TIB Participation Local Match Minimum Local Match
100.0% 0.0% 0%

Description of Improvements

Chip Seal of the following segments: 6th Street - Madison Ave to N C/L Garfield Avenue - Milwaukee Rd to W C/L