Region: East | Legislative District: 15 | Length: 0.00 mi. | FY 2023 Small City Preservation Program (SCPP) |
Existing Conditions |
Anticipated Project Costs
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 29,160 | 3,240 | 32,400 |
Right of Way | 0 | 0 | 0 |
Construction | 223,096 | 24,789 | 247,885 |
Project Totals | $252,256 | $28,029 | $280,285 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
90.0% | 10.0% | 5% |
Summary of Improvements
Description of Improvements
Prelevel and 2-inch overlay of the following segments: Chenaur Drive - Adam Park Dr to Sunset Way Sunset Way - Chenaur Dr to Kagley Wy Sunset Way - Chanaur Dr to 2nd Ave Birsh St - Ann St to Miles Dr Walnut St - Ann St to Miles Dr