Projects — TIB Funding Cycles
FY 2023 SCPP Selections
|
|
||||
Region: East | Legislative District: 12 | Length: 0.00 mi. | FY 2023 Small City Preservation Program (SCPP) |
Existing Conditions |
Anticipated Project Costs
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 13,290 | 0 | 13,290 |
Right of Way | 0 | 0 | 0 |
Construction | 119,626 | 0 | 119,626 |
Project Totals | $132,916 | $0 | $132,916 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
100.0% | 0.0% | 0% |
Summary of Improvements
Description of Improvements
N.Columbia Avenue provides local traffic from 3rd St NE to W. Elm St. Work will include crack sealing, minor pavement repairs and prelevel work, chip seal and fog seal, and pavement marking restoration.