Projects — TIB Funding Cycles
FY 2023 SCPP Selections
|
|
||||
Region: East | Legislative District: 12 | Length: 0.00 mi. | FY 2023 Small City Preservation Program (SCPP) |
Existing Conditions |
Anticipated Project Costs
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 10,346 | 1,150 | 11,496 |
Right of Way | 0 | 0 | 0 |
Construction | 142,251 | 15,805 | 158,056 |
Project Totals | $152,597 | $16,955 | $169,552 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
90.0% | 10.0% | 0% |
Summary of Improvements
Description of Improvements
Phase 1 of the the northeast residential corridor of Pateros to maintain and extend life of roadway. This corridor is a major local truck route for fruit trucks traveling to and from the orchards above hillside and is high priority for the City.