Existing Conditions |
Anticipated Project Costs
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 25,744 | 1,356 | 27,100 |
Right of Way | 0 | 0 | 0 |
Construction | 197,923 | 10,427 | 208,350 |
Project Totals | $223,667 | $11,783 | $235,450 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 0% |
Summary of Improvements
Description of Improvements
Overlay the existing roadway, with subgrade repair (digouts) where necessary. Recent completed work on Foster Avenue between 14th Ave and 17th Ave showed that the roadway lacks a gravel base and the HMA is less than 2 inches thick, so transition planning to connect to side streets would not provide a suitable base for paving. Instead of transition paving, subgrade repair consisting of 6-inches of crushed surfacing top course and 2-inches of HMA will be provided to connect to side streets.