Projects — TIB Funding Cycles
FY 2021 SCPP Selections
|
|
||||
Region: East | Legislative District: 7 | Length: 0.00 mi. | FY 2021 Small City Preservation Program (SCPP) |
Existing Conditions |
Anticipated Project Costs
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 3,123 | 0 | 3,123 |
Right of Way | 0 | 0 | 0 |
Construction | 44,765 | 0 | 44,765 |
Project Totals | $47,888 | $0 | $47,888 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
100.0% | 0.0% | 0% |
Summary of Improvements
Description of Improvements
The project provides double chip seal of the approved segments. The city is responsible for needed prep work.