Projects — TIB Funding Cycles
FY 2021 SCPP Selections
|
|
||||
Region: East | Legislative District: 16 | Length: 0.00 mi. | FY 2021 Small City Preservation Program (SCPP) |
Existing Conditions |
Anticipated Project Costs
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 2,850 | 150 | 3,000 |
Right of Way | 0 | 0 | 0 |
Construction | 118,750 | 6,250 | 125,000 |
Project Totals | $121,600 | $6,400 | $128,000 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 5% |
Summary of Improvements
Description of Improvements
The work includes pavement repair near the intersection with US 12, crack sealing, preleveling, chip seal, fog seal, and striping. Cameron Street is an important industrial collector in the City of Dayton that also serves the Boys and Girls Club, Port of Columbia, Dayton School District sports fields, and the Columbia County Transfer Station. The street experiences high traffic and is in need of preservation to maintain satisfactory pavement conditions and prevent future failure.