Projects — TIB Funding Cycles
FY 2021 SCPP Selections
|
|
||||
Region: East | Legislative District: 9 | Length: 0.00 mi. | FY 2021 Small City Preservation Program (SCPP) |
Existing Conditions |
Anticipated Project Costs
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 14,250 | 750 | 15,000 |
Right of Way | 0 | 0 | 0 |
Construction | 193,135 | 10,165 | 203,300 |
Project Totals | $207,385 | $10,915 | $218,300 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 5% |
Summary of Improvements
Description of Improvements
County chip seal followed by contractor slurry seal. This project goes right through the city's downtown central business district