Region: East   |   Legislative District: 15   |   Length: 0.19 mi. FY 2024 Small City Arterial Program (SCAP)

Existing Conditions

The pavement was last assessed in 2009 and was rated to be between 32-40. Naches Avenue is one of the major streets running north-south, connecting W. 1st Street and a large residential area to 9th Street and the Citys schools. There is currently no curb and gutter to collect storm drainage and protect the edges of the roads. The pedestrian access route has gaps and there is a lack of curb ramps and accessibility.

Project Funding

  TIB Funds Local Funds Total Costs
Design 93,005 4,895 97,900
Right of Way 0 0 0
Construction 713,545 37,555 751,100
Project Totals $806,550 $42,450 $849,000

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

This project will restore the condition of the roadway through full depth reclamation, install curb and gutter to protect the edges of the roadway and collect stormwater, and fill in gaps in the pedestrian access route and provide ADA compliant curb ramps.