Projects — TIB Funding Cycles
FY 2021 APP Selections
|
|
||||
Region: Northeast | Legislative District: 4 | Length: 0.00 mi. | FY 2021 Arterial Preservation Program (APP) |
Existing Conditions |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 41,020 | 17,580 | 58,600 |
Right of Way | 0 | 0 | 0 |
Construction | 487,631 | 208,984 | 696,615 |
Project Totals | $528,651 | $226,564 | $755,215 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
70.0% | 30.0% | 15% |
Summary of Improvements
Description of Improvements
The project provides pavement repair, crack seal and two-inch overlay of the street. No ADA upgrades are required.