City of Chewelah 1st Street West Reconstruction Webster Ave to Lincoln Ave |
Round 8 Physical Condition |
352,700 | 95.0% | 18,600 | 371,300 | |
City of Colville 7th Street Cedar to Madison Cedar St to Madison St |
Round 3 Physical Condition |
667,641 | 95.0% | 35,140 | 702,781 | |
City of Goldendale 2020 Byars Street Improvements Mill St to Columbus Ave |
Round 10 Physical Condition |
616,569 | 90.0% | 68,508 | 685,077 | |
Town of Lind Lind 5th Street Repairs N E St to N S St |
Round 9 Physical Condition |
416,723 | 100.0% | 0 | 416,723 | |
City of Mabton Main Street Reconstruction Project Washington St to SR 22 |
Round 1 Economic Vitality |
351,675 | 13.5% | 2,253,325 | 2,605,000 | |
City of Moxee Morrier Lane Extension Duffield Rd Roundabout to Mieras Rd |
Round 13 Physical Condition |
271,045 | 15.3% | 1,505,695 | 1,776,740 | |
City of Ritzville Main Ave Palouse St to Jackson St |
Round 12 Physical Condition |
330,600 | 95.0% | 17,400 | 348,000 | |
City of Soap Lake West Beach Park Access Improvements Main Ave W to Main Ave E |
Round 5 Physical Condition |
339,500 | 97.0% | 10,500 | 350,000 | |
City of Warden North County Road Improvements First St(SR 170) to N C/L |
Round 1 Physical Condition |
652,500 | 90.0% | 72,500 | 725,000 |