City of Kelso's LED Streetlight Conversion

S-W-188(001)-1

S-W-188(001)-1
LED Streetlight Conversion

PUD Owned

FY 2024 LED Program
Current Phase : Construction
Total TIB Funding : $145,589

County: Cowlitz   |   Legislative District: 19   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency KELSO
Funding Year 2024
Program LED
Current Phase Construction
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class Local Access
Type of Work
Project Contact Andy Hamilton
Contact Email andrewh@kelso.gov
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   09/12/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 10/01/2023 09/28/2023
Bid Auth. Approval 10/01/2023 09/28/2023
Construction Approval 10/01/2023 09/28/2023
Project Closeout 08/01/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 145,589 145,589
Other Construction 0 0
Total Construction 145,589 145,589
     
Total TIB Funding 145,589 145,589

Local Funding Partners

Funding Amount Percent
KELSO 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

The PUD will convert existing streetlights to LED.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments