Projects — TIB Project Information
TIB Project Information
City of Kelso's LED Streetlight Conversion
S-W-188(001)-1
S-W-188(001)-1
LED Streetlight Conversion
PUD Owned
FY 2024 LED Program
Current Phase : Audit
Total TIB Funding : $145,589
County: Cowlitz | Legislative District: 19 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/15/2024
Project Information
| Lead Agency | KELSO |
| Funding Year | 2024 |
| Program | LED |
| Current Phase | Audit |
| Legislative District | 19 |
| Congressional District | 3 |
| Federal Route Number | 9999 |
| Project Length | 0.10 mi. |
| ADT | 0 |
| Functional Class | Local Access |
| Type of Work | |
| Project Contact | Andy Hamilton |
| Contact Email | andrewh@kelso.gov |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 10/15/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 09/12/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 10/01/2023 | 09/28/2023 |
| Bid Auth. Approval | 10/01/2023 | 09/28/2023 |
| Construction Approval | 10/01/2023 | 09/28/2023 |
| Project Closeout | 12/01/2024 | 10/10/2024 |
| Audit Date | 10/15/2024 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 145,589 | 145,589 |
| Other Construction | 0 | 0 |
| Total Construction | 145,589 | 145,589 |
| Total TIB Funding | 145,589 | 145,589 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KELSO | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
The PUD will convert existing streetlights to LED.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||