TIB Project Information

City of Oak Harbor's LED Streetlight Conversion

S-W-157(001)-1

S-W-157(001)-1
LED Streetlight Conversion

PSE Owned

FY 2019 LED Program
Current Phase : Construction
Total TIB Funding : $220,000

County: Island   |   Legislative District: 10   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 03/31/2021

Project Information

Lead Agency OAK HARBOR
Funding Year 2019
Program LED
Current Phase Construction
Legislative District 10
Congressional District 2
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work
Project Contact Lisa Kinney
Contact Email lisa.kinney@pse.com
TIB Engineer Chris Langhoff
Last Payment Date 03/31/2021
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   01/17/2019
Delayed Project Date 07/01/2021  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/15/2019 03/11/2019
Bid Auth. Approval 02/15/2019 03/11/2019
Construction Approval 02/15/2019 03/11/2019
Project Closeout 06/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 220,000 220,000
Other Construction 0 0
Total Construction 220,000 220,000
     
Total TIB Funding 220,000 220,000

Local Funding Partners

Funding Amount Percent
OAK HARBOR 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

PSE will replace 627 HPS lights with LED street lights.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.