City of Oak Harbor's LED Streetlight Conversion
S-W-157(001)-1
S-W-157(001)-1
LED Streetlight Conversion
PSE Owned
FY 2019 LED Program
Current Phase : Construction
Total TIB Funding : $220,000
County: Island | Legislative District: 10 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 03/31/2021
Project Information
| Lead Agency | OAK HARBOR |
| Funding Year | 2019 |
| Program | LED |
| Current Phase | Construction |
| Legislative District | 10 |
| Congressional District | 2 |
| Federal Route Number | 9999 |
| Project Length | 0.10 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | |
| Project Contact | Lisa Kinney |
| Contact Email | lisa.kinney@pse.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 03/31/2021 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 01/17/2019 | |
| Delayed Project Date | 07/01/2021 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/15/2019 | 03/11/2019 |
| Bid Auth. Approval | 02/15/2019 | 03/11/2019 |
| Construction Approval | 02/15/2019 | 03/11/2019 |
| Project Closeout | 12/30/2025 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 220,000 | 220,000 |
| Other Construction | 0 | 0 |
| Total Construction | 220,000 | 220,000 |
| Total TIB Funding | 220,000 | 220,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| OAK HARBOR | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
PSE will replace 627 HPS lights with LED street lights.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||