There are no pedestrian access routes to Culbertson Park and the Crisis Support Network / Boys and Girls Club building on 2nd Street NE
Projects — TIB Project Information
TIB Project Information
City of Long Beach's 2nd Street NE Sidewalk
P-W-970(P01)-1
P-W-970(P01)-1
2nd Street NE Sidewalk
Washington Ave S to 600ft e/o Washington Ave S
FY 2025 Active Transportation Program
Current Phase : Design
Total TIB Funding : $336,300
County: Pacific | Legislative District: 19 | Project Length: 550.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/26/2024
Project Information
Lead Agency | LONG BEACH |
Funding Year | 2025 |
Program | ATP |
Current Phase | Design |
Legislative District | 19 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 550.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Brian Bollen |
Contact Email | bbollen@g-o.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 07/26/2024 |
Cultural Resource Assessment | CRA & BER |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/30/2024 | 12/20/2023 |
Bid Auth. Approval | 12/31/2024 | |
Construction Approval | 02/15/2025 | |
Project Closeout | 08/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 38,760 | 40,800 |
Right of Way | 0 | 0 |
Total Design | 38,760 | 40,800 |
Construction Engineering | 38,760 | 40,800 |
Construction Contract | 258,780 | 272,400 |
Other Construction | 0 | 0 |
Total Construction | 297,540 | 313,200 |
Total TIB Funding | 336,300 | 354,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LONG BEACH | 17,700 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 17,700 | 5.0% |
Project Description
Install a new 5 foot concrete sidewalk on the South side of 2nd Street NE from Washington Avenue to approximately 550 feet to the East
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Extends improvements;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |