Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Morton's Main Avenue

P-W-961(P06)-1

P-W-961(P06)-1
Main Avenue

Elementary School to Backstrom Park

FY 2019 Sidewalk Program
Current Phase : Construction
Total TIB Funding : $85,000

County: Lewis   |   Legislative District: 20   |   Project Length: 0.26   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 11/03/2022

Project Information

Lead Agency MORTON
Funding Year 2019
Program SP
Current Phase Construction
Legislative District 20
Congressional District 3
Federal Route Number 0508
Project Length 0.26 mi.
ADT 2,100
Functional Class Collector
Type of Work Pedestrian
Project Contact Tammy Clevenger
Contact Email cclerk@visitmorton.com
TIB Engineer Chris Langhoff
Last Payment Date 11/03/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 01/09/2018
Bid Auth. Approval 07/01/2021 08/04/2021
Construction Approval 07/30/2021 09/28/2021
Project Closeout 02/28/2023
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 42,500 68,799
Right of Way 0 0
Total Design 42,500 68,799
     
Construction Engineering 42,500 68,000
Construction Contract 0 390,220
Other Construction 0 0
Total Construction 42,500 458,220
     
Total TIB Funding 85,000 527,019

Local Funding Partners

Funding Amount Percent
MORTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
Federal Funding  442,019 83.9%
Total Local Funding 442,019 83.9%

Project Description

This project will include the construction of approximately 1,350 feet of six foot wide sidewalk on Main Avenue (SR 508) between the Community Center near 7th Street and the previous improvements in front of Morton Elementary School between 4th Street and 5th Street. The project will also include pedestrian crossing and storm drainage improvements.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments