The existing path shows several signs of deterioration and inaccessibility, including broken and uneven sidewalks and curbs (tripping hazards), intersections on a state highway with no pedestrian crossings or curb ramps, and a gap in the sidewalk system near 7th Street, where pedestrians do not have any dedicated path along the state highway.
Projects — TIB Project Information
TIB Project Information
City of Morton's Main Avenue
P-W-961(P06)-1
P-W-961(P06)-1
Main Avenue
Elementary School to Backstrom Park
FY 2019 Sidewalk Program
Current Phase : Construction
Total TIB Funding : $85,000
County: Lewis | Legislative District: 20 | Project Length: 0.26 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/03/2022
Project Information
Lead Agency | MORTON |
Funding Year | 2019 |
Program | SP |
Current Phase | Construction |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 0508 |
Project Length | 0.26 mi. |
ADT | 2,100 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Tammy Clevenger |
Contact Email | cclerk@visitmorton.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/03/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 01/09/2018 |
Bid Auth. Approval | 07/01/2021 | 08/04/2021 |
Construction Approval | 07/30/2021 | 09/28/2021 |
Project Closeout | 02/28/2023 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 42,500 | 68,799 |
Right of Way | 0 | 0 |
Total Design | 42,500 | 68,799 |
Construction Engineering | 42,500 | 68,000 |
Construction Contract | 0 | 390,220 |
Other Construction | 0 | 0 |
Total Construction | 42,500 | 458,220 |
Total TIB Funding | 85,000 | 527,019 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MORTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Federal Funding | 442,019 | 83.9% |
Total Local Funding | 442,019 | 83.9% |
Project Description
This project will include the construction of approximately 1,350 feet of six foot wide sidewalk on Main Avenue (SR 508) between the Community Center near 7th Street and the previous improvements in front of Morton Elementary School between 4th Street and 5th Street. The project will also include pedestrian crossing and storm drainage improvements.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |