Town of Coupeville's NW Coveland and 1st Street Sidewalk

P-W-827(P08)-1

P-W-827(P08)-1
NW Coveland and 1st Street Sidewalk

NW Coveland

FY 2023 Sidewalk Program
Current Phase : Construction
Total TIB Funding : $89,893

County: Island   |   Legislative District: 10   |   Project Length: 0.08   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency COUPEVILLE
Funding Year 2023
Program SP
Current Phase Construction
Legislative District 10
Congressional District 2
Federal Route Number 9999
Project Length 0.08 mi.
ADT 500
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Kelly Riepma
Contact Email publicworks@townofcoupeville.org
TIB Engineer Chris Langhoff
Last Payment Date

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 02/01/2022 02/11/2022
Bid Auth. Approval 02/15/2022 05/20/2022
Construction Approval 06/01/2022 08/26/2022
Project Closeout 02/28/2023
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 11,162 32,142
Right of Way 0 0
Total Design 11,162 32,142
     
Construction Engineering 16,213 5,000
Construction Contract 97,625 72,788
Other Construction 11,875 0
Total Construction 125,713 77,788
     
Funding Surplus - 46,982  
Total TIB Funding 89,893 109,930

Local Funding Partners

Funding Amount Percent
COUPEVILLE 20,037 18.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 20,037 18.2%

Project Description

Extend the existing sidewalk along NW Coveland by adding approximately 100 LF of sidewalk to connect to the wide asphalt shoulder on Madrona that is currently used for pedestrian access to Town. Install approximately 300 LF of concrete sidewalk connecting the existing sidewalk on N Main with that of NW 1st.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments